BPMN Training Part 6: Parallel Gateway
Related subfolder of the training project: "C06"
Chapter Overview
In this training chapter you get familiar with the BPMN Parallel Gateway.

A parallel gateway splits the process flow into two or more sequence flows, which are executed simultaneously. A joining parallel gateway waits for all incoming sequence flows to terminate before continue with one single output flow.
Sample BPMN Process Model
Tutorial Model: Automation/Business Process/Training/BPMN/Chapter/C06/ParallelGateway
Process Explanation:
-
The process is started in the lane of group "System" by a start event.
-
The sequence flow of the start event triggers the parallel gateway which splits the flow into two flows
-
a sequence flow that triggers the call activity "Enter and Verify first Data".
-
a sequence flow that triggers the call activity "Enter and Verify first Data".
-
The joining parallel gateway is in a wait state until both user tasks are completed.
-
Then the outgoing sequence flow of the joining parallel gateway triggers the end event.
Remark: Each call activity links to the global process "StartEndEvent_UserTask" which is explained in Chapter 2
Exercise
In this exercise you should remodel the process above and execute the process in the xAPPnow User Portal.
Exercise 1: Create the Business Process Model
Remark: Add your user name as a prefix to the model name to easily filter your personal process in the runtime environment (User Portal, Camunda).
-
Step 1: Right click at model tree folder "Automation/Business Process/Training/BPMN/Exercise/C06" to open context menu "Create Model"
-
Step 2: Enter model name "Username_ParallelGateway" and keep option "Model Type: Process" in dialog "Create Business Process Model"
-
Step 3: Click button "Search" to open dialog "Select Template"

-
Step 5: Select template "TMPL_SystemLane" in dialog "Select Template" with double click or click button "Select"

Exercise 2: Complete the Process Model
Complete the process model like the model above.
-
Step 1: Open the context menu of the start event and click at the parallel gateway to add it to the "System" lane
-
Step 2: Open the context menu of the parallel gateway and drag the call activity to the upper middle of the "System" lane
-
Step 3: Enter the label "Enter and Verify first Data" for the call activity
-
Step 4: Open the context menu of the parallel gateway and drag a second call activity "Enter and Verify second Data" to the lower middle of the "System" lane
-
Step 5: Select both call activities and configure a color using the context menu
-
Step 6: Open the context menu of call activity "Enter and Verify first Data" and drag a parallel gateway to join the splitted flows into the middle of the "System" lane
-
Step 7: Connect the outgoing flow of call activity "Enter and Verify second Data" also to the joining parallel gateway

-
Step 8: Open the context menu of the second parallel gateway and drag a third call activity "Enter and Verify thrird Data"
-
Step 9: Add an end event to terminate the process
-
Step 10: Link all three call activities with the previously created global process of excercise chapter 2 "Username_StartEndEvent_UserTask"
Exercise 3: Publish the Process Model
The process model has to be published into Camunda process engine. The process will be started online directly.
-
Step 1: Click button "Publish" in the toolbar to open the dialog "Publish Model"
-
Step 2: Enter username and password
-
Step 3: Publish the process with option "Start Process"
Exercise 4: Test the Process in User Portal
-
Step 1: Login into User Portal with user "john", who belongs to the group "TeamA". The task list contains 2 tasks "Enter Data" as we have two parallel call activities running.
-
Step 2: Execute the first task "Enter Data"
-
Step 3: Login into User Portal with user "jane", who belongs to the group "TeamB". The task list contains one user task "Verify Data"
-
Step 4: Login into User Portal with user "john", who belongs to the group "TeamA". Execute the second task "Enter Data" with different input data than with first task
-
Step 5: Login into User Portal with user "jane", who belongs to the group "TeamB". The task list now contains also the second user task "Verify Data"
-
Step 6: Execute this tasks to trigger the joining parallel gateway and the third call activity
-
Step 7: Login into User Portal with user "john", who belongs to the group "TeamA". Execute the third task "Enter Data" with different input data than with second task
-
Step 8: Login into User Portal with user "jane", who belongs to the group "TeamB". The task list now contains also the third user task "Verify Data"
-
Step 9: Execute this last task to trigger the end event which completes the process
See details in Exercise 5 of Chapter BPMN Introduction - Chapter 2: Start Event, User Task, End Event, Sequence Flow